A clear PEMS scope of work (SOW) is the foundation of a successful project. It helps vendors price accurately and avoids disputes during testing. It also makes sure the final system meets your permit.
Use the outline below as a starting point. Add or remove sections to suit your site, regulator and purchasing process.
1. Project Overview
Briefly describe the project and the parameters to monitor. For example: “Provide a PEMS for the site’s boilers to monitor NOx, CO, CO2 and SO2 and meet all regulatory requirements.”
2. Site Details for the PEMS Scope of Work
Give vendors enough information to understand your emission units. As a minimum, include:
- Number and type of units that need PEMS
- Fuel types and typical composition
- Unit specification sheets and operating range
- Emission control equipment, if any
- Available process instruments and control system (DCS/PLC) details
- Relevant permits and regulatory authority
3. Vendor Scope
State what the vendor must provide. A typical PEMS scope of work includes:
- Stack testing and data gathering for model development
- A PEMS model for each unit and pollutant
- A data acquisition system (DAS) that produces compliant reports
- Validation, RATA support and commissioning
- Training for site staff
- Warranty and ongoing support
You can name a model type: first principle, neural network or statistical. Alternatively, invite proposals for all three. See Types of PEMS for guidance.
4. PEMS Model Requirements
- The vendor must make the model open and document it fully.
- Your team should be able to see and change all constants, coefficients, equations and weighting factors.
- For neural network models, the vendor must explain the structure. It must also explain how it avoids over-training and keeps results stable.
- After training, your team should be able to update the model without relying fully on the vendor.
5. Data Acquisition for Model Development
Define the operating conditions for data collection. Typically, this means several loads, such as maximum, normal and reduced load. Plant availability will shape the final plan.
Allow the vendor to collect extra data sets if the model needs them. Also ask for a detailed test plan in advance so operations can prepare.
6. Model Validation and RATA
- Validate the model against reference methods. For example, use US EPA 40 CFR 60 Appendix A Methods 3A (O2), 10 (CO) and 7E (NOx).
- Then perform a Relative Accuracy Test Audit (RATA) after installation.
- Require relative accuracy within the applicable limit, such as EPA PS-16 or state rules. Use whichever is stricter.
- Also include any model fine-tuning in the project price.
- Agree in advance what to do if you cannot reproduce the test conditions.
7. Codes, Standards and Regulations
- US EPA 40 CFR Part 60 and Part 75, as applicable, and Performance Specification 16
- State or local agency rules, or international rules such as the Royal Commission Environmental Regulations (RCER)
- Electrical and equipment standards such as NEC, UL and ANSI
- ISA (International Society of Automation) standards for instruments
8. Reporting Requirements
List the reports your permit requires. These often include total emissions by pollutant and hourly, daily and monthly averages. They also cover exceedances and periods of shutdown or missing data. Finally, specify the units of measure.
9. Data Acquisition System (DAS)
- Real-time displays and alarms in the control room
- Operator settings for parameters and alarm conditions, with acknowledgement and reason codes
- Role-based security and an audit trail for data changes
- Standard regulatory reports plus custom queries and trends
- Data export and a link to the plant historian, such as OSIsoft PI or OPC
- A secure, supported server or virtual machine with backup and recovery
10. Schedule, Testing and Training
- Ask for a detailed execution plan that fits plant outages
- Then define factory and site acceptance tests (FAT/SAT) for your approval
- Train both general and advanced users, including model updates and system recovery
11. Commercial Terms
Include warranty, response times, liquidated damages and performance security. Also follow your organization’s standard terms. A common example is a 12-month warranty from commissioning. Another is capped liquidated damages for late completion.
12. Vendor Qualification
Ask vendors for references. Each reference should be an installation that the US EPA or an equivalent regulator has certified.